Cross onto Duck Key today and the drive feels almost suspiciously normal. No plywood decking rattling under your tires. No orange barrels funneling two lanes into one. For anyone who has lived on this island through the last five years, that alone is worth noticing, because for a long stretch, normal was not something Duck Key traffic did.
But normal is not the same as finished. The three interior bridges that turned daily errands into detours are done or close enough to it. The bridge that actually connects Duck Key to the rest of the Keys is not. It started construction in March, and it is not expected to wrap until around next spring. The headache didn't end. It moved to the one bridge everybody has to use.
The Three Bridges That Actually Got Finished
Duck Key sits on a cluster of small islands, Harbour Island, Plantation Island, Yacht Club Island, and Indies Island among them, stitched together by bridges built in 1955. Those bridges are old enough that the Florida State Historic Preservation Officer has twice found them individually eligible for the National Register of Historic Places. Old enough, also, that Florida Department of Transportation inspectors eventually flagged three of them, the Bimini Drive, Seaview Drive, and Harbour Drive bridges, as needing full replacement.
Monroe County awarded those three contracts to American Empire Builders in December 2020. What followed was not a quiet construction schedule. By August 2024, Keys Weekly was reporting that residents had lived through what the paper called years of "plywood bridge surfaces, detours and temporary one-way traffic patterns" as a fixture of daily life, not a temporary inconvenience. The Seaview Drive project alone had blown past a September 2024 contract deadline badly enough that the county began assessing liquidated damages against the contractor: $500 a day for the first fifteen days, $1,000 a day for the next fifteen, then $3,500 a day after that. The Duck Key Property Owners' Association, led at the time by Ron Oestreicher, spent months pushing the county for straight answers on real completion dates rather than the ones printed on paper.
That pressure, plus a new contractor rotation, eventually produced results. Here's where the three interior bridges stood as of this year, based on Monroe County's own project updates:
| Bridge | What Happened |
|---|---|
| Bimini Drive Bridge | Down to finishing touches by the time Keys Weekly checked in during August 2024 |
| Harbour Drive Bridge | Punch-list items completed and the project closed out in January 2026 |
| Seaview Drive Bridge | Fully opened to traffic on February 19, 2026, after a final milling and resurfacing change order |
Three bridges, five years, and a paper trail long enough that the Duck Key Security District Advisory Board still tracks bridge status as a standing agenda item at its meetings, with updates posted to the Duck Key Nextdoor page for residents who want to follow along in real time. That is not a community that treats bridge construction as background noise. It is one that has learned, the hard way, to watch it closely.
The Bridge Nobody Was Watching
Here is the part that gets missed if you only track the three bridges everyone was already frustrated about. While Harbour Drive and Seaview Drive were being closed out, a different project was quietly getting a contract of its own: repairs to the Toms Harbor Channel Bridge, the span that actually connects Duck Key to U.S. 1.
Monroe County awarded that contract to Freyssinet, Inc. for $1,196,041, the lowest of five bids received in December 2025, with approval landing on the county commission's January 28, 2026 agenda. The scope is narrower than the interior bridge replacements, mainly concrete spall repair on the beams, diaphragms, bents, and abutments rather than a full rebuild. But the contractor mobilized in March 2026, and the contract calls for 365 days to reach substantial completion. Do the math from a March start and that puts the target somewhere around March 2027.
Which means that as of this month, the island is roughly five months into a twelve-month project on the one bridge every resident and every guest actually has to cross to get anywhere. The interior bridges affected specific islands within Duck Key. This one is the front door. If you assumed the bridge saga wrapped up back in February, the correction is worth knowing before you plan around it.
What's Actually New While You Wait
The upside is that the wait now comes with better reasons to stick around than it used to.
Hawks Cay Marina finished a full relaunch in 2025, and it is not a cosmetic refresh. The property added a new waterfront promenade, 66 slips, a boat ramp, on-site fuel, and live bait, the kind of infrastructure that makes a difference to anyone who actually keeps a boat in the water rather than just looking at one. Hawks Cay's own events calendar now runs First Friday on the Promenade every month, 5 to 9 p.m., with local vendors and live entertainment that ranges from DJs to full bands. It's a low-key monthly reason to walk down to the docks even if you have no reservation and no boat.
Dinner got more serious, too. Chef Jeremy Ford, the Top Chef alum who holds a Michelin star at his Miami Beach restaurant Stubborn Seed, opened Salt + Ash at Hawks Cay, sourcing produce from his own property, Ford's Farm, and leaning on the same-day catch that only a restaurant sitting on the water can promise. Ford has talked about serving wahoo that came in on a Monday by Tuesday night, a supply chain most restaurants can only describe in marketing copy. For residents used to driving off the island for a serious dinner reservation, that's a genuine change in what's available without leaving the neighborhood.
There's also Angler & Ale for dockside, more casual dining, and Pilar Bar at the adults-only Oasis Cay pool if you want your evening quieter. And further out, Hawks Cay has confirmed that Coral Cay Adventure Park, described as the first attraction of its kind in the Florida Keys with waterslides, arcade space, and poolside dining built in, is set to open later this year, months before the Toms Harbor Channel Bridge work is even scheduled to finish.
One More Bridge, Then Normal
The honest version of this story is not "the construction is over." It's that Duck Key traded three finished bridge projects for one still-active one, and the active one happens to be the bridge that matters most for getting on and off the island. That's not a reason to dread the next several months. It's a reason to know what you're actually waiting on, and to notice that the island gave you a new marina, a monthly dockside gathering, and a Michelin chef's kitchen to enjoy in the meantime.
If you're weighing what any of this means for property here, whether it's timing a sale around the bridge calendar or figuring out what a home near the water is actually worth once the noise clears, that's a conversation worth having directly. Karan Moeller has spent decades working waterfront property across the Upper and Middle Keys and can walk you through what's changing on Duck Key specifically. Let's Connect.